Shoring Plans: When an Engineer Has to Design Them

Concrete slab cut and excavated on both sides of a post for new footings

In California, excavation shoring has to be designed by a registered engineer in three common cases: when the excavation is more than 20 feet deep, when the protection used is not one of the standard systems in the Cal/OSHA regulations, and when the building department requires engineered shoring plans to protect an adjoining building, property or street.

This guide covers the Cal/OSHA rules for protecting workers, the rules for protecting neighbors, what cities ask to see, and what an engineered shoring plan contains. It is drawn from the regulations and agency documents listed at the end, checked on November 23, 2026. It is general information and not safety direction for a specific excavation.

Two different questions

Shoring answers two separate questions, under two separate sets of rules:

  • Are the workers in the excavation protected? Cal/OSHA's Construction Safety Orders, in Title 8 of the California Code of Regulations.
  • Is the property next to the excavation protected? The building code, the Civil Code and the local building department.

An excavation can satisfy one and not the other. A trench shield is there to protect the workers inside it. It is not a support for the neighbor's footing.

Protecting workers: the Cal/OSHA rules

  • When protection is required. Under Section 1541.1, employees in an excavation are protected from cave-ins unless the excavation is entirely in stable rock, or it is less than 5 feet deep and a competent person's examination finds no indication of a potential cave-in.
  • The standard options. Protection can be sloping or benching, or a support or shield system. The regulation gives options that need no project-specific engineering: slopes and timber or aluminum hydraulic shoring from its appendices, the manufacturer's tabulated data, or other tabulated data approved by a registered professional engineer.
  • When an engineer designs it. A system that does not use one of those options is designed or approved by a registered professional engineer. The written design shows the sizes, types and configurations of the materials and identifies the engineer, and a copy is kept at the jobsite during construction.
  • More than 20 feet. Protective systems for excavations more than 20 feet deep are designed by a registered professional engineer.
  • The permit. A Cal/OSHA permit is required for excavations 5 feet or deeper that a person might enter.

Protecting what is next to the excavation

Section 1541 of the same safety orders addresses adjacent structures:

  • Where the stability of adjoining buildings, walls or other structures is endangered by the excavation, support such as shoring, bracing or underpinning is provided.
  • Excavating below the base of a footing or retaining wall, where that could pose a hazard, is not allowed unless a support system is provided, the excavation is in stable rock, or a registered professional engineer has determined that it poses no hazard.
  • Sidewalks and pavements are not undermined unless they are supported.

The building code adds its own requirement. Section 3307.1 of the California Building Code states that adjoining public and private property is to be protected from damage during construction, remodeling and demolition.

The 30-day notice to neighbors

California Civil Code Section 832 sets out what an owner owes the neighbor when excavating. As city handouts summarize it:

  • When notice is due. A 30-day written notice goes to the adjacent owner when the excavation will be deeper than the foundation of the adjoining building and closer to the property line than the excavation is deep.
  • What it says. The depth of the excavation and when it will begin.
  • Deep excavations. The Civil Code treats nine feet below the adjacent curb as the standard depth of foundations. An owner who excavates deeper than that, next to a building whose foundation reaches that depth or more, protects the neighbor's land and building at no cost to the neighbor, if given the license to enter.

Cities enforce this at the permit counter. The City of Culver City will not issue the permit until it has evidence of the notice, sent by certified mail, and has the receipt placed on the plans with a note that no excavation starts until 30 days after delivery.

What cities ask to see

AgencyWhen shoring plans are required
City of Manhattan BeachA shoring permit for all excavations, with three exceptions. The main one outside its sand section: a vertical cut of up to 4 feet with a sloped cut above it no steeper than 1 to 1, a total height of no more than 8 feet, and at least 5 feet of horizontal distance to daylight from adjacent footings. A geotechnical report with a slope stability analysis is the third route.
City of Newport BeachWhere the distance from the edge of the excavation to the property line is less than the depth of the excavation, shoring is required, with a shoring plan and calculations by a registered civil engineer.
County of Los AngelesIts sample submittal list notes that shoring plans and calculations may be required for excavations deeper than 4 feet, or that remove lateral support from a building, adjacent property or the public right of way.

The common thread is geometry. The closer the cut is to a property line or a footing, and the deeper it goes, the sooner an engineered design is required.

What an engineered shoring plan contains

Manhattan Beach's handout, updated in August 2023, gives a clear list. The shoring plans are prepared by a registered design professional and specify:

  • Dimensions and cross-sections.
  • Structural details and material specifications.
  • The method of shoring, and how the shoring will be removed.
  • The special inspection procedures.

With the plans, the city asks for structural calculations, a geotechnical report unless the design uses the building code's presumptive soil values, and a licensed surveyor's survey of the adjacent property line showing the neighboring buildings and their foundation locations and elevations. During the work, shoring construction is under continuous inspection by certified deputy inspectors, the design professional observes the work where the plans call for it, and a final report closes the permit.

Shoring in a remodel

The other kind of shoring holds up a building instead of holding back soil. When a bearing wall or a post is taken out, the floor or roof above has to be carried by temporary supports until the new beam, posts and footings are in. The engineer's part is to work out the load the temporary supports carry and where it goes, down to a surface that can take it.

Examples from our projects

On a residential addition and remodel in Orange, interior walls were removed to open the plan, with new beams and posts in their place and new footings below the posts. On a pool and deck project on a sloping lot in San Jose, the excavation ran along the concrete foundation wall of the existing house. Both are the kind of condition where the sequence of the work and the temporary support have to be thought through before anything is cut or dug.

Common questions

At what depth is shoring required in California?

Cal/OSHA requires cave-in protection in excavations 5 feet or deeper, and in shallower ones where a competent person finds signs of a potential cave-in. Protection can be sloping, benching, shoring or a shield.

When does shoring have to be designed by an engineer?

For excavations more than 20 feet deep, for systems outside the standard options in the regulation, and wherever the building department requires engineered shoring plans.

Do I need a permit for shoring?

A Cal/OSHA permit applies to excavations 5 feet or deeper that a person might enter. Cities such as Manhattan Beach also issue their own shoring permit.

Do I have to notify my neighbor before excavating?

Civil Code Section 832 calls for 30 days' written notice when the excavation is deeper than the neighbor's foundation and closer to the property line than it is deep.

Who is responsible for the neighbor's building?

Civil Code Section 832 divides the duty by depth. For an excavation deeper than the standard nine feet, next to a foundation that reaches that depth, the party excavating protects the neighbor's land and building. Beyond that it is a legal question for the owner's attorney.

How we help

Our structural engineering services include shoring design: temporary shoring for remodels and shoring for excavations, with drawings and calculations for the building department. The firm is licensed and insured. The soils data comes from a geotechnical engineer. We do not provide geotechnical services, and we coordinate with the geotechnical engineer on the project. Related reading: retaining wall permits in California.

Sources

Checked November 23, 2026. This article is general information, not safety direction, legal advice or advice for a specific project. Excavation safety on a site is governed by the Cal/OSHA regulations themselves and by the competent person and engineer responsible for that site.