A grading plan shows the shape of the ground before and after construction, written in elevations. Read it in this order: the existing contours, the proposed contours, the spot elevations, and then the slopes between them. Together they tell you where the building sits and where the water goes.
This guide explains what is on the sheet, the common abbreviations, how to work out a slope, and the numbers a reviewer checks. The examples of agency requirements are from the City of Orange grading plan checklist and the other sources listed at the end, checked on November 23, 2026.
Start with the frame of the sheet
- Scale and north arrow. Grading plans are drawn at an engineering scale. The City of Orange, for example, accepts 1 inch to 10, 20, 30 or 40 feet.
- Legend and abbreviations. Agencies ask for a legend that explains every symbol and abbreviation on the plan. Read it first, because abbreviations vary from one office to the next.
- Benchmark. The reference point all elevations are measured from. Every number on the plan depends on it.
- Existing and proposed. Existing features are usually drawn lighter or dashed, and proposed work is drawn solid. The City of Orange asks for existing features screened in grey and proposed features in solid black.
Contours
A contour is a line that joins points of the same elevation. The plan shows two sets: existing contours for the ground as it is, and proposed contours for the ground as it will be. The City of Orange asks for both at 1-foot intervals, with the existing contours carried at least 15 feet past the property line on every side.
- Spacing shows steepness. Contours close together mean a steep slope. Contours far apart mean flat ground.
- Bends show drainage. Where contours bend and point uphill, the ground forms a swale and water collects there. Where they bend and point downhill, the ground forms a ridge and water divides.
- Where the two sets differ, there is earthwork. A proposed contour that sits on the uphill side of the same existing contour means cut. One that sits on the downhill side means fill.

In the diagram: 1 existing contours, 2 proposed contours, 3 building pad and its elevation, 4 swale with flow arrows and an area drain, 5 retaining wall with top and bottom of wall elevations, 6 limit of grading.
Spot elevations and their abbreviations
Contours give the general shape. Spot elevations give the exact height at the points that matter. Each one is a number with a short label.
| Label | Meaning | Where you see it |
|---|---|---|
| FF | Finished floor | Inside the building outline. The floor level everything else is set against. |
| PAD | Pad elevation | The graded surface the building sits on, below the finished floor. |
| FG | Finished grade | Final ground level in landscape areas. |
| FS | Finished surface | Final level of paving and other hard surfaces. |
| TC | Top of curb | Along streets, drives and parking areas. |
| FL | Flow line | The low line of a gutter or swale, where the water runs. |
| TW | Top of wall | At retaining walls, usually paired with the grade at the bottom of the wall. |
| HP and LP | High point and low point | Where the drainage divides and where it collects. |
| IE or INV | Invert elevation | The inside bottom of a pipe at an inlet, manhole or outlet. |
| RIM | Rim elevation | The top of a manhole or drain inlet. |
These labels are the ones agency checklists call for by name. The City of Orange asks for pad and finished floor elevations, top of curb and flow line elevations at curbs and gutters, and high points and low points. The City of Cupertino asks for top of curb, finished grade, high points, low points, rim and invert elevations, and top of wall at retaining walls.
How to work out a slope
A slope is the change in elevation divided by the distance, written as a percent or as a ratio.
- Percent. A swale with a flow line of 101.50 at one end and 100.50 at the other, 100 feet apart, falls 1 foot in 100 feet. That is a 1 percent slope.
- Ratio. Graded slopes are written horizontal to vertical. A 2:1 slope runs 2 feet out for each foot up.
- Arrows. Flow arrows show the direction water runs. Follow them from each high point to an inlet, a swale or the street. Every part of the site should have a path out.
The numbers a plan checker looks for
These are from the City of Orange checklist, which cites the California Building Code for the grades next to the building. Other agencies set their own values, so use the checklist of the agency that will review the plan.
| Item | City of Orange value |
|---|---|
| Finished grade within 10 feet of the foundation | 5 percent minimum away from the building on pervious surfaces, 2 percent minimum on impervious surfaces |
| Swales, sheet flow and asphalt paving | 1 percent minimum |
| Concrete gutters in asphalt | 0.3 percent minimum |
| Parking stalls | 2 percent maximum |
| Parking lot crossfall | 5 percent maximum |
| Finished grade at property lines | At least 2 percent away from the line, with no drainage across lot lines |
| Cut and fill slopes | 2:1 maximum |
| Swales next to structures | At least 3 feet away |
A five-step read
- Orient. Find north, the scale, the legend and the benchmark.
- Read the existing ground. Trace the existing contours and see which way the site drains today, including water arriving from the neighbors.
- Find the pad and the finished floor. Compare them with the street. The County of Fresno, for example, asks for the finished floor to be above the crown of the adjacent street.
- Follow the water. Start at each high point and follow the arrows and flow line elevations to the outlet. Check that each slope meets the minimum.
- Check the edges. Look at the property lines, the walls, the graded slopes and the limit of grading. The edges are where a grading plan affects the neighbors.
What else is on the plan
A complete grading plan also carries the earthwork volumes in cubic yards, split into cut, fill, import and export, the disturbed area, cross-sections at the project boundaries, the drainage devices, and the erosion control measures. The City of Orange requires the signature and stamp of the registered civil engineer on every sheet.
Examples from our projects
For a 16-unit townhome development in Palm Springs, the civil scope included the grading plan and grading sections along with the civil site plan for the tentative tract map. For an industrial development in Rialto, it included the on-site precise grading plan and the final drainage study.
Common questions
What do the numbers on a grading plan mean?
They are elevations: heights above the benchmark, in feet. The label next to each number says what is being measured, such as the finished floor or the top of a curb.
What does FF mean on a grading plan?
Finished floor. It is the elevation of the building floor, and the surrounding grades are set to drain away from it.
How do I tell which way water flows?
Water runs from higher elevations to lower ones, at right angles to the contours. Flow arrows and flow line elevations show the intended path.
What does a 2:1 slope mean?
Two feet horizontal for each foot vertical.
What is the difference between existing and proposed contours?
Existing contours show the ground as surveyed. Proposed contours show the ground after grading. The difference between them is the cut and fill.
Who prepares a grading plan?
A civil engineer. Agencies such as the City of Orange require the registered civil engineer's signature and stamp on all sheets.
How we help
We prepare grading and drainage plans for permit as part of our civil engineering services, and we answer the plan check comments on our scope. Related reading: grading permits in California and grading permits in Los Angeles County.
Sources
Checked November 23, 2026. This article is general information, not advice for a specific project. Requirements differ by agency and change over time, so confirm them with the agency that will review your plans.
- City of Orange Public Works, Grading Permit Plans Preparation guidelines and checklist
- City of Cupertino, Grading and Drainage Plan Application Checklist, January 2023
- County of Fresno, Grading and Drainage Plan Checklist, revised October 26, 2023
- City of San Diego, survey deliverables checklist, November 2025, on elevation labels such as TC, FL, IE, TW and FS
- California Building Standards Commission, 2025 California Building Standards Code (Title 24), including California Building Code Section 1804.4, Site grading