Grading Permits in Los Angeles County: Requirements and Process

Foundation excavation with footing trenches and reinforcing steel for a residential rebuild in Altadena

In unincorporated Los Angeles County, grading needs an approved grading plan and a grading permit unless the work falls under one of the exemptions in Section J103.2 of the County grading code. The plan is reviewed by Los Angeles County Public Works, and the permit is issued by the local Building and Safety district office.

This guide covers who reviews what, the exemptions, what to submit, the review steps and the items that most often hold up approval. It applies to the unincorporated areas, such as Altadena, and to cities that contract with the County for building services. The City of Los Angeles issues grading permits through its own Department of Building and Safety under its own code. The guide was checked on November 23, 2026 against the County sources listed at the end.

Who reviews the grading plan

  • Single lots. The Building and Safety district office for the area. Its drainage and grading plan check engineer reviews the plan for completeness and for compliance with the County codes, including the Low Impact Development requirements.
  • Subdivisions and Conditional Use Permits. The Land Development Division of Public Works. Once it approves the plan, the applicant takes the approved package to the district office, or to the city's public works department, to obtain the permit.

Plans for unincorporated areas are submitted online through EPIC-LA, the County's electronic permitting portal. Contract cities use the County's separate web application for those cities.

When a grading permit is not required

County Public Works lists these exemptions, with the details and conditions in Section J103.2:

  • Grading in an isolated, self-contained area.
  • Excavation for the construction of a structure.
  • Cemetery graves and refuse disposal sites.
  • Mining, quarrying and the processing or stockpiling of rock, sand, gravel, aggregate or clay.
  • Excavations for soils exploration. Access roads and pads built for the exploration are not exempt.
  • Excavations under 50 cubic yards.
  • Fill that is not meant to support a structure and does not obstruct a drainage course.

Each exemption carries conditions on depth, slope and location. Read the section itself, or ask the district office, before treating a job as exempt.

Regular grading and engineered grading

The County sorts grading into two kinds. Grading of more than 5,000 cubic yards, and grading that will support a structure, is engineered grading. Engineered grading plans have to be prepared by a registered civil engineer. A building pad is grading that will support a structure, so the pad for a new building is engineered grading whatever the volume.

What to submit

For a single-lot grading plan check, Building and Safety asks for:

  • A completed grading permit application and the plan check fee.
  • Two sets of legible plans.
  • One soils report that is less than one year old.
  • Two sets of supplemental documents, such as the hydrology report, HydroCalc results, Low Impact Development reports, easements and deed restrictions.

The Land Development Division lists four items as the minimum to begin its review: the grading plan, the plan check fee, the approved planning documents and an approved hydrology study. Its plan standards call for general notes, a benchmark, an engineering scale of 1 inch to 40 feet or larger with a graphic scale, a vicinity map, and title blocks for the civil engineer, the geotechnical consultant, the surveyor and the owner.

The review, step by step

  1. Completeness screening. The application package, plans, soils report, supplemental documents and fee are checked in.
  2. Plan review. The engineer marks corrections on the plans and on a correction sheet.
  3. Corrections. The plans are corrected and resubmitted together with the agency approvals.
  4. Final check. Agency approvals are confirmed, and the plans are rechecked and approved.
  5. Permit. The project is ready for grading permit issuance.

Where the grading is tied to a building permit, rough grade approval is required before the building permit is issued. The grading permit is not finalized, and any bond is not released, until the inspector finalizes the related permits.

Other approvals that run alongside

Grading approval can depend on other agencies. The County names the Department of Regional Planning, the Geotechnical and Materials Engineering Division, the Fire Department and the California Coastal Commission, and the applicant receives a referral sheet that lists what is needed. The Land Development Division notes that most grading has planning and zoning implications, so the land use approval from Regional Planning comes before grading begins. Work in a streambed can bring in the Army Corps of Engineers and the California Department of Fish and Wildlife.

Items that hold up approval

These come from the County's Grading Review Sheet. The published sheet is the 2023 code edition, revised February 9, 2023, so confirm the current sheet with the plan checker.

  • Rainy season. Grading between October 15 and April 15 requires an erosion and sediment control plan before the permit is issued.
  • One acre or more. Projects that disturb one acre or more file a Notice of Intent with the state and obtain a WDID number before grading approval. See our guide to SWPPP requirements in California.
  • Permit security. A bond is required for grading that exceeds 1,000 cubic yards, or as the Building Official requires.
  • Low Impact Development. Residential projects of four units or fewer implement at least two LID best management practice alternatives. Designated projects that disturb one acre or more and add more than 10,000 square feet of impervious area meet the LID requirements.
  • Signatures. Grading plan sheets and calculations are signed and stamped by the responsible California registered professionals. Hydrology and hydraulic calculations are signed and stamped by a California registered civil engineer.
  • Slopes. Slopes steeper than 2 horizontal to 1 vertical need stability data. Fill over terrain steeper than 5 to 1, or deeper than 5 feet, is keyed and benched.
  • Drainage away from the building. The ground falls at least 6 inches within the first 10 feet from the foundation, and pads slope at least 2 percent toward the outlet.
  • Expiration. A grading permit application expires if no permit is issued within one year of the application date. A Land Development Division grading plan approval expires two years after approval.

Examples from our projects

Altadena is unincorporated, so rebuilds there are permitted through the County. We prepared the civil drawings for permit on two fire rebuilds in Altadena, one with structural and civil engineering and one with structural, civil and MEP engineering.

Common questions

Do I need a grading permit in Los Angeles County?

Yes, for all grading in the unincorporated areas unless the work falls under an exemption in Section J103.2 of the County grading code.

How much dirt can I move without a permit?

The County lists excavations under 50 cubic yards as exempt, subject to the conditions in Section J103.2. Fill has its own conditions. Confirm with the district office before starting.

What is engineered grading?

Grading of more than 5,000 cubic yards, or grading that will support a structure. The plans are prepared by a registered civil engineer.

Is a soils report required?

Building and Safety lists a soils report less than one year old in its submittal requirements for grading plans.

Does this apply in the City of Los Angeles?

No. The City of Los Angeles reviews grading through its own Department of Building and Safety.

Can I grade during the rainy season?

Yes, with an erosion and sediment control plan in place before the permit is issued for grading between October 15 and April 15.

How we help

We prepare grading and drainage plans, hydrology and drainage studies and erosion control plans for projects in Los Angeles County, and we answer the plan check comments on our scope. The soils report comes from a geotechnical engineer. We do not provide geotechnical services, and we coordinate with the geotechnical engineer on the project. Related reading: grading permits in California and civil plan check corrections.

Sources

Checked November 23, 2026. This article is general information, not advice for a specific project. Requirements change over time, so confirm them with Los Angeles County Public Works and the district office that will review your plans.