In Orange County, a Water Quality Management Plan (WQMP) is required for new development and significant redevelopment, and the full version applies to Priority Projects. In north and central county, those include new development that creates 10,000 square feet or more of impervious surface and redevelopment that adds or replaces 5,000 square feet or more. The city where the project sits, or the County in unincorporated areas, reviews the plan and has to approve it before building or grading permits are issued.
This guide covers what a WQMP is, the Priority Project thresholds, the difference between north and south Orange County, what the plan has to show and when it is due. It was checked on November 23, 2026 against the County and city sources listed at the end.
What a WQMP is
A project WQMP is the plan for managing the quality of stormwater and urban runoff from a site after construction, once the building is occupied. It describes the best management practices, or BMPs, that will be built and then maintained over the life of the project. It is a different document from the SWPPP, which covers the site during construction.
The rules come from the municipal stormwater permits issued by the Santa Ana and San Diego Regional Water Quality Control Boards. The County's Model WQMP and Technical Guidance Document turn those permits into a method, and each city applies them through its own checklist and template.
North county and south county use different documents
The dividing line is El Toro Road.
| Area | Guidance documents |
|---|---|
| North and central Orange County, north of El Toro Road | Model WQMP dated May 2011 and Technical Guidance Document dated December 2013. |
| South Orange County, south of El Toro Road | Model WQMP and Technical Guidance Document dated July 2026, which together serve as the BMP Design Manual for the south county jurisdictions. A separate Hydromodification Management Plan and the South Orange County Hydrology Model also apply. |
The south county documents now carry a July 2026 date, so a template from an earlier south county project should be checked against the current edition. The County notes that requirements vary slightly between jurisdictions and directs applicants to the agency with authority over the site.
Which projects are Priority Projects
The City of Orange publishes the test as a list of questions. One yes makes the project a Priority Project:
- New development that creates 10,000 square feet or more of impervious surface, whether commercial, industrial or residential.
- Automotive repair shops.
- Restaurants where the land area of the development, including parking, is 5,000 square feet or more.
- Hillside development of 5,000 square feet or more on known erosive soils or where the natural slope is 25 percent or more.
- Impervious surface of 2,500 square feet or more within or next to an Environmentally Sensitive Area, or discharging directly to one.
- Parking lots with 5,000 square feet or more of impervious surface exposed to stormwater.
- Streets, roads, highways and freeways with 5,000 square feet or more of paved surface.
- Retail gasoline outlets of 5,000 square feet or more with 100 or more vehicles a day.
- Significant redevelopment: adding or replacing 5,000 square feet or more of impervious surface on a developed site. Routine maintenance is excluded.
- Any project the City Engineer determines will adversely affect water quality.
The categories come from the Model WQMP, so other north county cities use a similar test, but each city has its own checklist. Use the one for the city that will issue the permit.
Projects below the thresholds
A project that is not a Priority Project can still need a shorter plan. The City of Irvine requires a Non-Priority Project Water Quality Plan where the project needs a discretionary action that includes a precise grading plan, and in a few other cases. The City of Tustin requires a WQMP for all new development and redevelopment, with an exemption for smaller single-family homes: a house of 5,500 square feet or less of interior space, and additions within set limits.
What a Priority Project has to do
- Retain or biotreat the design storm. The City of Tustin states the requirement in one line: Priority Projects have to infiltrate, harvest and reuse, evapotranspire or biofilter the 85th percentile storm event on site.
- Use low impact development. Site design that limits impervious surface, and BMPs that mimic the hydrology of the site before development.
- Control pollutant sources. Source control BMPs keep pollutants out of contact with runoff. The City of Orange gives education, sweeping and covers as examples.
- Address hydromodification where it applies. The goal the City of Tustin gives is that post-development peak flows for the 2-year storm do not exceed pre-development conditions.
- Plan for maintenance. The WQMP names the BMPs to be maintained over the life of the project, and cities provide operation and maintenance templates and covenant forms for it.
When the WQMP is due
- Preliminary WQMP. With the application for discretionary approval. The City of Orange recommends preparing it early in conceptual design, and notes that a missing preliminary WQMP can delay project approval.
- Final WQMP. Approved before building or grading permits are issued. The City of Irvine adds that the plans submitted for plan check have to be consistent with the approved WQMP.
The BMPs take up area on the site, and infiltration depends on the soil. That is why the WQMP is prepared with the grading and drainage plan, and why it starts with the site layout. See our guide on when to start WQMP preparation.
Examples from our projects
On an event venue tenant improvement in Irvine, the civil scope included grading and drainage design, stormwater management and a Water Quality Management Plan prepared to Orange County and City of Irvine requirements. On a new residential development in Garden Grove, the civil scope covered the grading and drainage plans, the WQMP and the hydrology report.
Common questions
Who needs a WQMP in Orange County?
New development and significant redevelopment projects. Priority Projects prepare a full project WQMP. Many smaller projects prepare a shorter non-priority plan, depending on the city.
What is the threshold for a Priority Project?
In the north county test, the main ones are 10,000 square feet or more of new impervious surface for new development, and 5,000 square feet or more of added or replaced impervious surface for redevelopment. Restaurants, parking lots, hillside sites and gasoline outlets have their own thresholds.
When is the WQMP due?
A preliminary WQMP goes in with the discretionary application. The final WQMP has to be approved before building or grading permits are issued.
Is a WQMP the same as a SWPPP?
No. The WQMP covers the site after construction. The SWPPP covers the site during construction.
Does a single-family house need a WQMP?
It depends on the city and the size. Tustin, for example, exempts a single-family home of 5,500 square feet or less of interior space unless the City finds a pollutant concern.
Are the rules the same across Orange County?
No. North and central county and south county use different Model WQMP and Technical Guidance Documents, and each city has its own checklist and template.
How we help
We prepare WQMP and LID plans together with the grading and drainage plans and the hydrology study for projects in Orange County, and we answer the plan check comments on our scope. Infiltration design relies on the soils report, which comes from a geotechnical engineer. We do not provide geotechnical services, and we coordinate with the geotechnical engineer on the project.