Title 24 Lighting Acceptance Testing: What It Is, Who Does It

Clerestory windows near the ceiling of an office space in Los Alamitos

Title 24 lighting acceptance testing is a field test of the installed lighting controls, done after the controls are installed, by a lighting controls Acceptance Test Technician certified through a provider approved by the California Energy Commission. The engineer's drawings and compliance forms do not replace it, and the engineer does not perform it.

This guide covers where the test sits among the Energy Code forms, which controls are tested, who may test, and how to keep it from holding up the final. It applies to nonresidential work under the 2025 Energy Code and was checked on November 23, 2026 against the Energy Commission sources listed at the end.

Three kinds of forms, three different people

Form familyWhenWho completes it
NRCC, certificate of complianceWith the plans, for the permit. For indoor lighting it is the NRCC-LTI-E.The designer of the lighting.
NRCI, certificate of installationAfter installation.The installing contractor.
NRCA, certificate of acceptanceAfter installation, when the controls are tested in the field.A certified Acceptance Test Technician.

The Energy Commission states that acceptance testing is a mandatory requirement of the Energy Code for lighting controls and for mechanical systems. For lighting controls, the test has had to be done by a certified technician since July 2014.

Which lighting controls are tested

  • Shut-off controls. Occupant sensors and automatic time switches. Form NRCA-LTI-02-A.
  • Daylight responsive controls. Form NRCA-LTI-03-A.
  • Demand responsive controls. Form NRCA-LTI-04-A.

The Energy Commission's quick reference cards also state that only a certified lighting technician may test indoor and outdoor lighting systems and controls. Which tests apply follows from the controls the design calls for. A lighting alteration that complies by reducing power needs fewer controls, and so fewer tests. See Title 24 lighting requirements for tenant improvements.

There is a small-job exception: acceptance testing is not required where a lighting alteration adds controls to 20 or fewer luminaires across the whole project.

Who may perform the test

  • Acceptance Test Technician (ATT). A technician certified to perform nonresidential acceptance tests. There are two kinds: lighting controls and mechanical systems.
  • Acceptance Test Employer (ATE). Every technician has to work for a certified employer, including a technician who is self-employed.
  • Certification provider (ATTCP). An organization approved by the Energy Commission to train, certify and oversee technicians and employers. For lighting controls, the Energy Commission's cards list CALCTP and NLCAA.

The technician can be the installing technician or a third party. The Energy Commission says a third party is allowed and not required. The completed NRCA forms are submitted to and recorded by the certification provider.

To find or verify a technician, use the provider directories linked from the Energy Commission's program page and check that the name and certification number appear there.

What the technician needs from the design

The test checks the installed controls against the design, so the drawings and the certificate of compliance are the reference. From the design side, these help:

  • A lighting plan that shows each control and the luminaires it controls.
  • The daylit zones marked where daylight responsive controls apply.
  • A control sequence a contractor can program: time-out periods, schedules, and what the demand response signal does.
  • A fixture schedule that matches the NRCC-LTI-E.

Keeping it from holding up the final

  1. Identify the tests at design. The controls on the drawings set the tests. List them in the specifications.
  2. Put the technician in the electrical bid. The test is a cost and a visit, and someone has to carry it.
  3. Program before the test. Sensors and time switches are set and working before the technician arrives.
  4. Have the forms recorded. The certificates of acceptance go to the certification provider. Ask the building department what it wants to see at the final inspection.

Examples from our projects

On a hair salon tenant improvement in Arcadia, the electrical design covered the lighting, and the energy compliance documentation went in with the plans for plan check. On a restaurant tenant improvement in Costa Mesa, the lighting design was part of the electrical scope. Field acceptance testing was not part of our scope on either project. It belongs to the construction side.

Common questions

Who performs Title 24 lighting acceptance testing?

A lighting controls Acceptance Test Technician certified by a provider the Energy Commission has approved.

Can the electrician who installed the controls test them?

Yes, if that electrician is a certified Acceptance Test Technician working for a certified employer.

Does the engineer do the acceptance test?

No. The designer prepares the certificate of compliance for the permit. The acceptance test is a separate field role.

Is acceptance testing required for a small lighting job?

Not where the alteration adds controls to 20 or fewer luminaires across the whole project.

What is the difference between NRCC, NRCI and NRCA?

The certificate of compliance goes with the plans, the certificate of installation follows the installation, and the certificate of acceptance records the field test.

Is there acceptance testing for HVAC too?

Yes. Mechanical systems have their own acceptance tests and their own certified technicians.

How we help

We prepare the lighting and electrical plans and the Title 24 compliance documents as part of our electrical engineering scope for tenant improvements. We prepare the compliance forms only. Acceptance testing in the field is done by a certified Acceptance Test Technician and is not part of our scope.

Sources

Checked November 23, 2026. This article is general information, not advice for a specific project. Requirements change over time, so confirm them with the building department that will review your plans.