A hydrology study calculates how much stormwater reaches a site and leaves it, before and after development. The reviewing agency uses it to confirm that the pipes, inlets and basins on the plans are large enough, and that the project does not send more water onto its neighbors or into the street than the rules allow.
Agencies use several names for it: hydrology study, hydrology report, drainage study, drainage report. This guide covers what the study contains, the method behind it, which manual applies, and when Southern California agencies ask for one. It was checked on November 23, 2026 against the sources listed at the end.
Hydrology and hydraulics
A study has two halves, and it helps to keep them apart.
- Hydrology answers how much water. It turns rainfall on a drainage area into a flow rate.
- Hydraulics answers what carries it. It sizes the pipes, gutters, inlets and basins for that flow.
The method in one line
For small drainage areas the usual tool is the Rational Method: Q = CIA. Peak flow equals a runoff coefficient, times rainfall intensity, times drainage area. The coefficient rises as ground is covered with roofs and paving, which is why development increases runoff and why the study compares existing and proposed conditions. The County of Los Angeles grading review sheet, for example, allows the Rational Method for subareas under 40 acres.
Which manual applies
There is no single statewide design storm for site drainage. Each county flood control agency publishes its own manual, and cities usually point to the county's.
| County | Manual |
|---|---|
| Los Angeles | The 2006 Hydrology Manual, which covers the Rational Method and the county's Modified Rational Method. |
| Orange | The Hydrology Manual, with the Rational Method and the Unit Hydrograph Method, and the Local Drainage Manual, second edition, adopted May 25, 2021. |
| San Diego | The Hydrology Manual dated April 2026. |
| San Bernardino | The 2026 edition of the Hydrology Manual. |
The manual sets the storm to design for. OC Public Works summarizes the levels in its Local Drainage Manual this way: storm drains with tributary areas under 640 acres are designed for at least a 10-year storm below the top of curb, catch basins in a sump for a 25-year storm, and habitable structures get a 100-year level of flood protection.
What is in the study
- Drainage area maps. One for existing conditions and one for proposed, showing each subarea, its size and where it drains.
- Off-site flows. Water that arrives from neighboring land or the street and has to pass through or around the site.
- Runoff calculations. Peak flows for the design storms, existing against proposed.
- Hydraulic calculations. Sizes for the storm drains, inlets and swales, and for detention or retention where the agency requires it.
- Conclusions. How the proposed drainage meets the agency's criteria, and how the building pads are protected.
The calculations carry a license. The County of Los Angeles review sheet asks for hydrology and hydraulic calculations to be signed and stamped by a California registered civil engineer.
When an agency asks for one
- With a grading plan. The Land Development Division of Los Angeles County Public Works lists an approved hydrology study among the minimum items needed to begin its grading plan review. County Building and Safety lists the hydrology report and HydroCalc results among the supplemental documents for a grading plan check.
- To set the pad elevation. The City of Orange requires the minimum pad elevation to meet the Orange County Local Drainage Manual.
- For storm drains. The City of Orange asks for storm drain profiles for pipes 8 inches and larger, with the design flow and velocity noted. Those numbers come from the study.
- Near a mapped flood zone. The agency can ask for a flood analysis in addition to the site hydrology.
Hydrology study and WQMP: not the same document
Both deal with stormwater, and both go in with the grading plan, but they answer different questions.
| Hydrology study | WQMP | |
|---|---|---|
| Question | Will the site flood, or flood someone else? | Will the runoff carry pollutants off the site? |
| Storm | Large design storms, such as the 10-year, 25-year and 100-year events. | The small, frequent storm. The City of Tustin, for example, states it as the 85th percentile storm event. |
| Result | Pipe, inlet and basin sizes, and protected pad elevations. | Treatment and retention measures, and a maintenance plan. |
The two have to agree, because one basin or planter can serve both purposes. See our guide to WQMPs in Orange County.
Examples from our projects
For a new residential development in Garden Grove, the civil scope included the hydrology report together with the grading and drainage plans and the WQMP. For an industrial development on a 1.05-acre site in Rialto, it included the final drainage study with the on-site precise grading plan and the final WQMP.
Common questions
What is a hydrology study?
A calculation of how much stormwater reaches and leaves a site before and after development, with the sizing of the drainage system that carries it.
Is a hydrology study the same as a drainage study?
Agencies use the names for the same kind of report. Some use hydrology for the flow calculations and drainage or hydraulics for the pipe sizing.
Who prepares a hydrology study?
A civil engineer. The County of Los Angeles, for example, asks for the calculations to be signed and stamped by a California registered civil engineer.
What storm is a site designed for?
It depends on the agency. In Orange County, local storm drains are designed for a 10-year storm, sumps for a 25-year storm, and buildings are protected in a 100-year storm.
What is the Rational Method?
The formula Q = CIA: peak flow equals a runoff coefficient times rainfall intensity times drainage area.
Is a hydrology study the same as a WQMP?
No. The hydrology study covers flooding in large storms. The WQMP covers water quality in small, frequent storms.
How we help
We prepare hydrology and drainage studies with the grading and drainage plans and the WQMP, following the county or city manual that applies to the site, and we answer the agency comments on our scope. Related reading: stormwater drainage design explained.
Sources
Checked November 23, 2026. This article is general information, not advice for a specific project. Each agency sets its own method and design storm, so confirm them with the agency that will review your plans.
- Los Angeles County Public Works, water resources publications, including the 2006 Hydrology Manual
- OC Public Works, Hydrology, on the Orange County Hydrology Manual
- OC Public Works document summarizing the hydrologic protection levels of the Local Drainage Manual
- San Diego County Public Works, Hydrology Manual, April 2026
- San Bernardino County, Hydrology Manual, 2026 edition
- Los Angeles County Public Works, Land Development Division, Grading
- Los Angeles County Public Works, Building and Safety, Drainage and Grading Plan Check
- County of Los Angeles Public Works, Grading Review Sheet, on the Rational Method and on signed and stamped calculations
- City of Orange Public Works, Grading Permit Plans Preparation guidelines and checklist
- City of Tustin, Water Quality Management Plan, on the 85th percentile storm event