Available Fault Current and AIC Rating, Explained

Open electrical panel in a wall during a salon tenant improvement

Available fault current is the largest current the electrical system can deliver into a short circuit at a given point. The AIC rating is the largest fault current a breaker, fuse or panel is rated to interrupt. The rule is simple: the rating has to be at least as large as the current available where the equipment is installed.

This guide explains the two numbers, where each one comes from, what the electrical code requires, and what California building departments ask to see. It was checked on November 23, 2026 against the sources listed at the end.

The two numbers

TermWhat it isWhere it comes from
Available fault currentThe current that would flow if a short circuit happened at that point. Usually given in amperes or thousands of amperes (kA).The utility's system and transformer, reduced by the conductors between the transformer and the equipment.
Interrupting rating (AIC)The highest fault current the device is rated to interrupt at its rated voltage. AIC stands for ampere interrupting capacity.The manufacturer. It is marked on the equipment.

A breaker that is asked to interrupt more than its rating can fail to clear the fault. That is the reason the comparison is made on the drawings, before anything is ordered.

What the electrical code requires

These provisions are from the California Electrical Code as quoted in a 2022 code handout by the state's Department of Health Care Access and Information. The 2025 code is now in effect, so confirm the wording against it.

  • Section 110.9, interrupting rating. Equipment intended to interrupt current at fault levels has to have an interrupting rating, at nominal circuit voltage, at least equal to the current available at its line terminals.
  • Section 110.24, field marking. Service equipment at other than dwelling units is marked in the field with the available fault current and the date the calculation was performed. The calculation is documented and kept available.
  • Section 110.24, modifications. When a change to the installation affects the available fault current at the service, the value is verified or recalculated and the marking is updated.
  • Section 110.16, service equipment of 1,200 amperes or more. A permanent label lists the nominal system voltage, the available fault current at the service overcurrent devices, their clearing time and the date of the label.
  • Unmarked devices. Under Sections 240.83 and 240.60, a circuit breaker carries its interrupting rating on it when the rating is other than 5,000 amperes, and a fuse when it is other than 10,000 amperes.

What plan check asks to see

  • City of Calabasas. The plans indicate the maximum available fault current, as provided by the utility company, at each service-entrance section. Where the available fault current is above 10,000 amperes, or the service is 400 amperes or larger, the plans are prepared and stamped by a registered design professional or a licensed electrical contractor.
  • City of Sacramento. The single-line drawing shows the interrupting ratings of the service and the panelboards.
  • County of Ventura. The plans give the serving voltage, the amperage and the short-circuit current available from the utility, and the interrupting capacity of the equipment.

In practice the two numbers sit side by side on the single-line diagram: the available fault current at the service and at each panel, and the rating of the equipment at the same point.

Where to get the available fault current

  1. Ask the utility. The serving utility provides the available fault current at the service point. Calabasas words its requirement that way.
  2. Carry it downstream. Conductors add impedance, so the available current falls with distance from the transformer. The engineer calculates the value at each panel from the conductor sizes and lengths shown on the diagram.
  3. Compare. At every point, the equipment rating is checked against the calculated value.

When the number changes

Section 110.24 treats the value as something to keep current. Work that can change it includes a service upgrade, a replacement utility transformer, and new distribution equipment. Existing equipment is part of the question: a panel that was adequately rated when it was installed is checked again when the service ahead of it changes.

Examples from our projects

For fire damage repair at a multifamily building in Sacramento, the electrical scope included a replacement 400-ampere service with its meters and panels. For a commercial kitchen in San Diego, the single-line diagram started at the 3,000-ampere building service and ran to a new kitchen sub-panel.

Common questions

What does AIC stand for?

Ampere interrupting capacity. It is the fault current a breaker, fuse or panel is rated to interrupt.

Is the AIC rating the same as the breaker size?

No. The breaker size, such as 100 amperes, is the current it carries in normal use. The interrupting rating, such as 10,000 or 22,000 amperes, is the fault current it can safely interrupt.

Who provides the available fault current?

The utility provides it at the service. The engineer calculates it at the equipment downstream.

Does a house need an available fault current label?

The field marking in Section 110.24 applies to service equipment at other than dwelling units.

What happens if the available fault current is higher than the rating?

The equipment does not meet Section 110.9, and the design has to change: equipment with a higher rating, or another approach the engineer and the plan checker accept.

How we help

We prepare single-line diagrams with the available fault current and the equipment ratings, together with the panel schedules and load calculations, as part of our electrical engineering scope. Related reading: how to read a panel schedule and code-compliant electrical systems in California.

Sources

Checked November 23, 2026. This article is general information, not advice for a specific project. Electrical code editions and agency requirements change, so confirm them with the building department that will review your plans.