A Qualified SWPPP Developer (QSD) writes the stormwater pollution prevention plan for a California construction site. A Qualified SWPPP Practitioner (QSP) carries it out on site: the inspections, the sampling and the upkeep of the controls. A QSD may do both jobs. A QSP may do only the QSP's.
This guide covers the two roles, how each is certified, what can be delegated, and who stays responsible. It follows the State Water Board's guidance on the Construction Stormwater General Permit, listed at the end and checked on November 23, 2026.
The two roles side by side
| Question | QSD | QSP |
|---|---|---|
| What the role does | Develops the SWPPP. | Implements it on site: visual inspections, sampling, and the SWPPP and best management practices. |
| Can it do the other role? | Yes. A QSD can perform QSP duties. | No. A QSP can perform only QSP duties. |
| Inspections named in the guidance | The same, when acting as the QSP. | Monthly site inspections, and inspections before a qualifying precipitation event. |
| Can it be an outside consultant? | Yes. | Yes. |
A project can have more than one of each. The State Water Board's guidance allows a discharger to hire several QSDs and QSPs, as long as their contact information is in the SWPPP.
When the roles are needed
Both roles come with coverage under the Construction Stormwater General Permit, which a project needs when it disturbs one acre or more, or is part of a larger common plan of development that does. A site below that line has no state requirement for either role, though the city or county can still require an erosion and sediment control plan. See SWPPP requirements in California.
How each is certified
- Through CASQA. The California Stormwater Quality Association certifies both roles. A candidate meets a prerequisite, completes a course led by a trainer of record, passes the exam and registers with CASQA.
- By self-certification. California licensed professional engineers and professional geologists can self-certify in the state's online system, SMARTS, after reviewing the licensing board's self-directed training material.
- Keeping it current. A CASQA-certified QSD or QSP completes 6 hours of continuing education each year and renews online every 2 years. Self-certified holders have no continuing education requirement.
To check someone's standing, the guidance points to the CASQA qualification directory and to the public user menu in SMARTS. The State Water Board can rescind a certification for willful or negligent violations, false or misleading information, fraud or deception, or a failure to use reasonable care.
What the QSP can hand to others
With the discharger's authorization, the QSP can delegate visual inspections, sampling and the day-to-day work of the SWPPP and the best management practices.
- Who can be a delegate. Construction staff who are on site often, such as a superintendent, project manager or foreman, or a stormwater professional who is not yet certified.
- Training first. Delegates need foundational and site-specific training, and may inspect only after the QSP has trained them on that site.
- The QSP stays in it. The QSP reviews the delegates' work and confirms that they understand and can perform the tasks.
The inspections on the calendar
Every site under the permit, at every risk level, has weekly inspections and inspections before, during and after a qualifying precipitation event. The QSP's own inspections are monthly and before each event. A qualifying precipitation event is a forecast of at least a 50 percent chance of precipitation with 0.5 inch or more within 24 hours. Pre-event inspections fall within 72 hours before it, inspections during the event happen at least once every 24 hours, and post-event inspections fall within 96 hours after.
Who is responsible
Neither the QSD nor the QSP holds the permit. The discharger does, and the State Water Board's guidance is direct that the discharger remains ultimately responsible for compliance. The documents are filed by the discharger's Legally Responsible Person. See WDID numbers, the Notice of Intent and SMARTS.
For an owner or a general contractor, that settles how to set the job up:
- Engage the QSD while the grading plan is being drawn, so the SWPPP and the erosion control sheets agree.
- Name the QSP before construction starts, and decide who on site will be the trained delegate.
- Keep both names and their contact details current in the SWPPP.
Common questions
What is the difference between a QSD and a QSP?
The QSD develops the SWPPP. The QSP implements it on site. A QSD can do both. A QSP cannot develop the plan.
Can one person be both the QSD and the QSP?
Yes, if that person is a QSD.
Does a civil engineer need a separate QSD certificate?
A California licensed professional engineer can self-certify in SMARTS after reviewing the licensing board's training material.
Can the superintendent do the inspections?
As a trained delegate of the QSP, yes. The QSP's own monthly and pre-event inspections remain with the QSP.
Who is responsible for compliance?
The State Water Board's guidance says the discharger remains ultimately responsible for permit compliance.
Is a QSD needed for a site under one acre?
Not under the state permit, unless the site is part of a larger common plan of development.
How we help
We prepare SWPPPs with a Qualified SWPPP Developer, together with the grading plan and the erosion and sediment control plan, so the documents agree. Related reading: what BMPs are in construction.
Sources
Checked November 23, 2026. This article is general information, not advice for a specific project. Requirements change over time, so confirm them with the State Water Board and the Regional Water Board for your site.