WDID Number, Notice of Intent and SMARTS, Explained

3D view of a new industrial development with a large workshop, a smaller two-suite building, parking and a fenced yard

A WDID number is the identification number California issues when a construction site obtains coverage under the Construction Stormwater General Permit. It is the proof of coverage. To get it, the project's Legally Responsible Person files a Notice of Intent and the other registration documents in SMARTS, the state's online system, before construction begins.

This guide covers the three terms, who files, what is filed, what happens when the project changes, and how coverage ends. It follows the State Water Board's guidance listed at the end, checked on November 23, 2026.

The three terms

TermWhat it is
NOI, Notice of IntentThe application for coverage under the permit. It is one of the Permit Registration Documents.
SMARTSThe Stormwater Multiple Application and Report Tracking System, the State Water Board's online system where the documents are filed and the reports are submitted.
WDIDThe waste discharge identification number the system issues once State Water Board staff have processed the registration documents.

No paper certificate is issued. The system emails the users linked to the project, and the NOI receipt letter can be printed from SMARTS. That letter, with the WDID on it, is the document to show a city or county that asks for proof of coverage.

Who needs one

A project needs coverage, and so a WDID, when it disturbs one acre or more of land, or is part of a larger common plan of development that does. Local agencies check for it. The County of Los Angeles grading review sheet, for example, calls for a filed Notice of Intent and a WDID number before grading approval on sites that disturb one acre or more. See SWPPP requirements in California for the threshold and the waiver for small sites with low rainfall erosion risk.

Who files

  • Legally Responsible Person (LRP). The person legally designated to sign, certify and electronically submit the documents. For a corporation or limited liability company it is a responsible corporate officer. For a partnership or sole proprietorship it is a general partner or the proprietor. For a public agency it is a principal executive or an authorized public employee.
  • Duly Authorized Representative. The LRP may designate a representative to sign, certify and submit on its behalf.
  • Accounts are personal. A SMARTS account cannot be shared. If the representative changes, the new person creates an account and requests access through the state's stormwater help desk.

The engineer and the Qualified SWPPP Developer prepare much of what is filed. They are not the filer. The filing is the discharger's act, through its LRP.

What is filed, and when

The Permit Registration Documents are submitted electronically in SMARTS before construction begins:

  • The Notice of Intent.
  • The risk assessment.
  • Post-construction plans and calculations. Preliminary ones are allowed, with an update filed within 14 days after the local stormwater agency approves the final ones.
  • A site map.
  • The SWPPP.
  • A signed certification and the first annual fee.

A project that crosses into more than one Regional Water Board's area files separately for each. The fee schedule is set in state regulation and revised each year. The first annual fee is paid with the NOI and is based on the area remaining to be disturbed, and annual invoices continue until coverage is terminated.

When the project changes: the Change of Information

The NOI is not filed once and forgotten. A Change of Information is filed in SMARTS to:

  • Change the start or end date.
  • Increase or reduce the acreage.
  • Switch the site to inactive status. For a suspension of 30 days or more, the filing includes a revised SWPPP, a revised site map and photographs of the temporary stabilization.
  • Update the post-construction plans.
  • Start dewatering.

Adding parcels means amending the registration documents 14 days before construction starts on them. Amending the SWPPP alone does not need a Change of Information, but the amended SWPPP is uploaded to the WDID.

A sale is handled by how much is sold. For a partial sale, the seller reports the new owner's name, address and phone number on a Change of Information. For a full sale, the seller files a Notice of Termination, and the new owner files new registration documents and receives a new WDID.

Annual reports

An annual report is due by September 1 each year for the period from July 1 through June 30. It is required where coverage lasted at least 90 days in the reporting period. Sites under the small construction erosivity waiver do not file one.

Ending coverage: the Notice of Termination

Coverage does not end when construction ends. The discharger submits a Notice of Termination in SMARTS, and the Regional Water Board approves it. A notice is approved automatically after 30 calendar days unless the Regional Water Board denies it, returns it or accepts it for review within that time. All outstanding invoices have to be paid before coverage can be terminated, and invoices keep coming until the termination is approved.

The sequence on a typical project

  1. The civil engineer establishes the disturbed area on the grading plan.
  2. The Qualified SWPPP Developer prepares the risk assessment and the SWPPP.
  3. The LRP, or its representative, files the registration documents in SMARTS and pays the fee.
  4. The system issues the WDID.
  5. The WDID goes on the plans or to the agency that asked for it, and grading approval follows the agency's own review.
  6. During construction: inspections, any Change of Information, and the annual report.
  7. At the end: the Notice of Termination.

Common questions

What is a WDID number?

The waste discharge identification number issued in SMARTS when the registration documents for the Construction Stormwater General Permit are processed. It is the proof of coverage.

How do I get a WDID number?

The Legally Responsible Person files the Notice of Intent, the risk assessment, the site map, the SWPPP, the post-construction documents, the certification and the fee in SMARTS before construction begins.

Can my engineer file the NOI for me?

The LRP files, or designates a Duly Authorized Representative to file. The engineer and the QSD prepare the technical documents.

Is there a paper permit?

No. The NOI receipt letter is printed from SMARTS.

What happens to the WDID when the property is sold?

On a full sale the seller files a Notice of Termination and the new owner files for a new WDID. On a partial sale the seller files a Change of Information.

When is the annual report due?

By September 1, for July 1 through June 30.

How we help

We prepare SWPPPs with a Qualified SWPPP Developer, together with the grading plan and the erosion and sediment control plan, and we give the owner's representative the documents to file. The filing in SMARTS is made by the owner's Legally Responsible Person or its representative. Related reading: QSD vs QSP.

Sources

Checked November 23, 2026. This article is general information, not advice for a specific project. Requirements and fees change over time, so confirm them with the State Water Board and the Regional Water Board for your site.