The California Building Code requires the ground next to a foundation to slope away from the building at 5 percent or more for at least 10 feet. That is a fall of 6 inches in 10 feet. Impervious surfaces within 10 feet, such as walks and patios, slope away at 2 percent or more.
This guide covers the rule, what to do when there is no room for 10 feet, the exception for climate and soil, and what cities and counties add on top. The code text is as quoted in the agency documents listed at the end, checked on November 23, 2026.
The rule, in Section 1804.4
| Surface | Minimum slope away from the building | Distance |
|---|---|---|
| Ground next to the foundation | 5 percent, which is 1 unit vertical in 20 horizontal | At least 10 feet, measured perpendicular to the face of the wall |
| Impervious surfaces: walks, patios, driveways | 2 percent | Within 10 feet of the foundation |
| Swales used to carry the water away | 2 percent along the swale | Where the swale is within 10 feet of the foundation |
The California Residential Code states the same thing for houses as a drop: at least 6 inches of fall within the first 10 feet. The County of Los Angeles grading review sheet uses that wording.
When there is not 10 feet
A side yard narrower than 10 feet cannot provide that distance, so the code gives a second way to comply. Where physical obstructions or lot lines prohibit 10 feet of horizontal distance, a 5 percent slope is provided to an approved alternative method of diverting water away from the foundation. A swale or an area drain between the building and the property line is the usual example.
A 5-foot side yard works out like this: the ground falls 5 percent from the building to a swale, which is 3 inches in 5 feet, and the swale then runs at 2 percent or more toward the street or a drain.
The exception for climate and soil
Section 1804.4 carries an exception: where climatic or soil conditions warrant, the slope of the ground away from the foundation may be reduced to not less than 1 unit vertical in 48 horizontal, which is 2 percent. Agencies decide when conditions warrant it, and they handle it differently.
What local agencies add
The state code sets the floor. The agency that reviews the grading plan publishes the values it will accept, and they are not all the same.
| Agency | What it publishes |
|---|---|
| City of Orange | Within 10 feet of the foundation, 5 percent minimum on pervious surfaces and 2 percent minimum on impervious surfaces. Swales at 1 percent minimum, and at least 3 feet from structures. |
| OC Public Works | Its standard grading correction list asks for typical lot drainage details at 5 percent minimum away from the foundation on pervious surfaces and 2 percent on impervious surfaces. |
| County of Los Angeles | At least 6 inches of fall within the first 10 feet from the foundation, and pads sloped at least 2 percent toward the outlet. |
| City of Covina | Drainage slope away from structures and property lines at 5 percent minimum. |
| City of Menlo Park | 5 percent on pervious surfaces and 2 percent on impervious surfaces, within 10 feet of the structure. |
| City of Hemet | An engineering standards update dated May 23, 2024 allows 2 percent on pervious surfaces and 1 percent on impervious surfaces next to the foundation, under the conditions that document sets. |
Hemet's values show why the local document matters: a slope that passes there would draw a correction in Orange.
Where the water goes next
Sloping the ground away from the building is the first half. The second half is giving the water a path off the lot. The California Green Building Standards Code, Section 4.106.3, requires the construction plans to show how the site grading or drainage system will manage all surface water flows to keep water from entering buildings. A grading plan does that with flow arrows, swales, area drains and an outlet. Agencies also keep runoff on its own lot: the City of Orange asks for finished grade to fall at least 2 percent away from property lines, with no drainage across lot lines.
How it shows on a grading plan
- Finished floor and pad elevations. The floor is set above the ground around it.
- Spot elevations at the building corners and 10 feet out. The difference between them is the fall.
- Slope labels and flow arrows. The percent and the direction, on each side of the building.
- A typical lot drainage detail. A section through the side yard that shows the slope, the swale and the distance to the property line.
See how to read a grading plan for the abbreviations.
Examples from our projects
For a new residence in Garden Grove, the civil scope was the grading and drainage plans with the stormwater management and the hydrology report. For two fire rebuilds in Altadena, one with structural and civil engineering and one with structural, civil and MEP engineering, we prepared the civil drawings for the County permit.
Common questions
How much should the ground slope away from a house?
At least 6 inches in the first 10 feet, which is 5 percent, under the California codes. Paved surfaces within 10 feet slope at least 2 percent.
What is the minimum slope for concrete next to a building?
2 percent away from the building for impervious surfaces within 10 feet of the foundation, under Section 1804.4.
What if my side yard is narrower than 10 feet?
The ground slopes 5 percent to an approved alternative, such as a swale or drain, that carries the water away.
Can the slope be reduced to 2 percent?
The code allows it where climatic or soil conditions warrant. Ask the reviewing agency whether it applies the exception.
Can water drain onto the neighbor's lot?
Agencies such as the City of Orange do not allow drainage across lot lines.
How we help
We prepare grading and drainage plans for new buildings, additions and ADUs as part of our civil engineering services, to the values of the agency that will review them. Related reading: ADU grading and drainage plans and stormwater drainage design explained.
Sources
Checked November 23, 2026. This article is general information, not advice for a specific project. Code editions change and each agency sets its own values, so confirm them with the agency that will review your plans.
- OC Public Works, Site Grading for Drainage Around Building policy, updated November 7, 2024, quoting Section 1804.4 of the California Building Code and Section 4.106.3 of the Green Building Standards Code
- City of Hemet, Site Grading for Drainage Around Buildings, engineering standards supplemental update, May 23, 2024
- City of Orange Public Works, Grading Permit Plans Preparation guidelines and checklist
- OC Public Works, Grading Plan Standard Correction List
- County of Los Angeles Public Works, Grading Review Sheet
- City of Covina Public Works, Grading Plan Submittal Guidelines
- City of Menlo Park, Grading and Drainage Guidelines